Campus Design

The design agreement for Paul Cavin Architecture, LLC was approved by the BCC on April 23, 2019.  The project was initiated with the strategy to deliver the project with three General Maximum Price (GMP) packages.   As the design has been completed and phasing has been determined, there are now 5 GMP packages. 

GMP Plans:

  • GMP1: Buildings 8C, 603 and 604

         Completed 5/24/19

  • GMP2: Building 8

        Completed 7/26/19

  • GMP3: Buildings 602, 605 (600 and 601 Demo)

        Scheduled to be completed 9/13/19

  • GMP4: Site Improvements

        Scheduled to be completed 9/13/19

  • GMP5: Buildings 600 and 601

        Scheduled to be completed 9/13/19

 

GMP Construction and Estimated timeline:

  • GMP1: Buildings 8C, 603 and 604

        8C Construction: 9/9/19 – 1/17/20

        603 Construction: 9/24/19 - 3/2/20

        604 Construction: 10/22/19 – 3/20/20

  • GMP2: Building 8

        Building 8 Construction: 9/25/19 – 4/14/20

  • GMP3: Buildings 602 and 605 (Assumption of relocation of existing occupants for concurrent construction)

        602 Construction: 11/01/19 – 5/15/20

        605 Construction: 11/01/19 – 5/15/20

  • GMP4: Site Improvements

        Site Construction: 10/25/19 – 1/31/20

  • GMP5: Buildings 600 and 601

        600 and 601 Construction: 11/22/19 – 5/15/20

It is Important to note that these estimates were made PRIOR to construction starting and assuming there are not significant areas that are identified in addition to current understanding once work has started.

As of September 9, 2019, the Campus has broke ground, and we are on our way to building and restoring lives of homeless individuals and families in our community.