FINAL SUBDIVISION MAP SUBMITTAL DATES
|
INITIAL SUBMITTAL |
CONSTRUCTION PLAN REVIEW MEETING |
| January 09. 2012 | February 02, 2012 |
| January 23, 2012 |
February 16, 2012 |
| February 13, 2012 | March 08, 2012 |
| February 27, 2012 | March 22, 2012 |
| March 12, 2012 | April 05, 2012 |
| March 26, 2012 | April 19, 2012 |
| April 09, 2012 | May 03, 2012 |
| April 23, 2012 | May 17, 2012 |
| May 14, 2012 | June 07, 2012 |
| May 29, 2012 | June 21, 2012 |
| June 11, 2012 | July 05, 2012 |
| June 25, 2012 | July 19, 2012 |
| July 09, 2012 | August 02, 2012 |
| July 23, 2012 | August 16, 2012 |
| August 13, 2012 | September 06, 2012 |
| August 27, 2012 | September 20, 2012 |
| September 10, 2012 | October 04, 2012 |
| September 24, 2012 | October 18, 2012 |
| October 08, 2012 | November 01, 2012 |
| October 22, 2012 | November 15, 2012 |
| November 13, 2012 | December 06, 2012 |
| November 26,2012 | December 20, 2012 |
| December 10, 2012 | January 03, 2013 |
| December 24, 2012 | January 17, 2013 |
| These dates apply to subdivisions only in the unincorporated areas of Washoe County. |
|
| Initial Submittal dates occur on the second and fourth Monday of the month. | |
| Construction Plan Review Meetings occur on Thursdays, 24 calendar days after the initial submittal. |
|
| Dates are adjusted as necessary for holidays. |