Approved CIP Plan for Fiscal Years 2012-2016
|
|
Interstate 80 Design-Build Traffic Control ALERT Southeast Connector Information |
|
|
|
PROJECT TITLE
|
DIST.
|
PHASE |
SCHEDULE COMMENTS
|
% COMPLETE
|
|
GENERAL PROJECTS
|
||||
| 350 Center Street Window Replacement | 3 | Completed | Funding for only 2 floors approved. | 100% |
| 75 Court St - HVAC Energy Upgrade | 3 | Complete | Finalizing Punchlist | 100% |
| Courts Master Planning | Various | Planning | 98% | |
| Sparks Justice Court | 4, 5 | Design | 90% | |
| Special Assessment District No. 32 | 5 | Bidding |
Approx. 12.3 miles of gravel roads to be graded and paved including drainage improvements. Bids to be opened on July 28, 2011. |
|
| 1001 E 9th St Bldg A re-roof | 3 | Planning |
Construction material ready and waiting for construction due to budget. Anticipating starting in May |
100% |
| Longley Lane Truck Wash Environmental Improvements | 3 | Design |
Going out for bid April 2012 |
100% |
|
PARKS PROJECTS
|
||||
|
PROJECT TITLE
|
DIST. | PHASE | SCHEDULE COMMENTS | % COMPLETE |
| North Valley Water Park | 5 | Design | Project in design | 25% |
| ARRA fire rehabilitation projects |
Various |
Construciton |
Projects under construciton through 2013 |
70% |
|
LIBRARY PROJECTS
|
||||
|
PROJECT TITLE
|
DIST. | PHASE | SCHEDULE COMMENTS | % COMPLETE |
|
Downtown Branch - HVAC Energy Upgrade |
3 |
Completed |
Finalizing punchlist |
100% |
|
Verdi Community Center/Library expansion |
5 |
Completed |
100% |
|
|
SHERIFF PROJECTS
|
||||
|
PROJECT TITLE
|
DIST. | PHASE | SCHEDULE COMMENTS | % COMPLETE |
| Detention Security Upgrades | 3 | Completed | Finalizing punchlist | 100% |
| 911 Parr Boulevard Re-roof | 3 | Design | Labor bids to be sought in May | 45% |
|
FIRE PROJECTS
|
||||
| PROJECT TITLE | DIST. | PHASE | SCHEDULE COMMENTS | % COMPLETE |
| SFPD Station 36-Arrowcreek/Thomas Creek |
2 |
Completed |
Finalizing punchlist |
100% |
|
LAKE TAHOE EROSION CONTROL PROJECTS |
||||
| PROJECT TITLE | DIST. | PHASE | SCHEDULE COMMENTS |
% COMPLETE |
| Fairview/Fairway Phase III |
1 |
Planning |
Developing existing conditions analysis memorandum including PLRM and selection of alternatives. Design: 2012, Construction: 2013 |
80% |
| Gonowabie Rd Slope Repair |
1 |
Bidding |
Proposal to reject initial bid result in the agenda item for BCC's April 24th meeting. Re-advertising on April 26th and bid opening on May 3rd with target start date of construction on June 4th. |
30% |
| Central Incline Village Phase I |
1 |
Planning |
Start basemaps and field work for existing conditions. Design: 2013, Construction: 2014 |
20% |
| Centrail Incline Village Phase II |
1 |
Planning |
Start basemaps for existing conditions. |
5% |
|
PEDESTRIAN AND BICYCLE CONSTRUCTION PROJECTS |
||||
| Cold Springs Valley Pedestrian Path Project |
5 |
Design |
Project on hold. Evaluation of alternative sidewalk alignments. Target completion of alternative analysis is Spring, 2012 |
|