Another beautiful day in the Truckee Meadows!
Another beautiful day in the Truckee Meadows!


CAPITAL PROJECTS
 

Dwayne Smith, P.E.
Engineering and Capital Projects Division Director

Kimble O. Corbridge, P.E., CFM
Acting County Engineer

 

MISSION STATEMENT

To develop and implement the County's Capital Improvement program to meet our customers' functional needs, budgetary constraints, and scheduling requirements. The Capital Projects Division is responsible for constructing and remodeling county facilities to meet the needs of our growing community by implementing Washoe County`s Capital Improvement Plan. 

 

     Approved CIP Plan for Fiscal Years 2013-2017


June 2013

 Interstate 80 Design-Build Traffic Control ALERT                       Southeast Connector Information

                                        

PROJECT TITLE
DIST.
PHASE
SCHEDULE COMMENTS
% COMPLETE

GENERAL PROJECTS

350 Center Street Window Replacement 3 Completed Funding for only 2 floors approved. 100%
Courts Master Planning Various Planning   98%
Sparks Justice Court 4, 5 Completed 100%
230 Edison HVAC Replacement 3 Design

Project in design.

85%

PARKS PROJECTS

PROJECT TITLE
DIST. PHASE SCHEDULE COMMENTS % COMPLETE
North Valleys Water Park 5 Construction Currently under construction. 50%
ARRA fire rehabilitation projects

 Various

Construction

Projects under construciton through 2013.

90%

Wilbur D May Museum

3

Design 

Design complete. Project went out to b and bids were opened. Project was over budget and currently awaiting direction.

90%

NSP3 842 Spokane

3

Construction 

Construction in progress.

98% 

NSP3 Zephyr Properties

3

Construction

Awarding bid.

0% 

Ballardini Trailhead

 1

Design 

Design completed. Out to bid in April, 2013

50%

LIBRARY PROJECTS

PROJECT TITLE
DIST. PHASE SCHEDULE COMMENTS % COMPLETE

Sparks Library Meeting Room Remodel

3

Design

50%

SHERRIFF PROJECTS

PROJECT TITLE
DIST. PHASE SCHEDULE COMMENTS % COMPLETE
Remodel Housing Unit 3 3 Design Changing jail cells to office space. Construction documents being prepared. 30%
911 Parr Boulevard Re-roof 3 Design Labor bids to be sought in May. 100%
Remodel 140 Jail Cell Bunks 3 Design 50%

FIRE PROJECTS

PROJECT TITLE DIST. PHASE SCHEDULE COMMENTS % COMPLETE
Station 35 Verdi

5

Design Project in design.

20% 

LAKE TAHOE EROSION CONTROL PROJECTS

PROJECT TITLE DIST. PHASE SCHEDULE COMMENTS

% COMPLETE
(Phase only)
 

Fairview/Fairway Phase III

1

Construction

Project awarded by BCC on April 9, 2013. Construction scheduled to begin May 14, 2013.

15%

Central Incline Village Phase I

 1 

 Planning 

Developing alternatives. Design: 2013,
Construction: 2014.

70% 

Central Incline Village Phase II

Planning

Developing alternatives. Design 2013.
Construction 2015.

80% 

PEDESTRIAN AND BICYCLE CONSTRUCTION PROJECTS

For information contact Capital Projects at 328-2040